Wednesday, November 26, 2008

Eighth Street Bridges — February?

The City of Port Angeles and Exeltech, the project manager, are now estimating February 2nd as the date the two Eighth Street bridges will be open. This estimate is based on not having any weather-related delays.

This project has taken longer than originally expected, but so far it’s still within its $24.6 million budget. $21.6 million is from the State Department of Transportation; $3 million is from city funding.

The construction company, Parsons RCI, has requested additional funding to cover the increased costs of materials. Glen Cutler, Public Works Director, expects the project to stay within budget even after approving the additional money to Parsons.

Part of the delay has been the result of having to redesign the foundation abutment because of poor soil on the west side of the Tumwater Creek Bridge.

Labels: , , , ,

Friday, July 20, 2007

Information on Eighth Street Bridges

Next Thursday, July 26th from 4:30 to 7 p.m. there will be an open house regarding the eighth street bridge closures. It will be held at the city council chambers, 321 East Fifth Street.

If you have questions about the construction schedule, traffic revisions, detour routes, etc., this meeting should have the information you need. Representatives from the city will be at the meeting as well as representatives from Exeltech, the construction management firm handling the project. The public will be able to talk informally and/or provide written comments. There will be a short presentation on the project, followed by a question and answer session.

Check here for more information.